EN

RU CN

Date:

21.11.2025

Reading time:

6 minutes

Author:

Daniil Kadyrov

Managing Partner

How to Recover Payment for Additional Work Under a Contract For Work and Services?

Contract Law Contract for work and services

Date:

21.11.2025

Reading time:

6 minutes

FAQ

What If the Client Claims the Cost of Additional Work Was Overstated?

In this case, the court may appoint a construction and technical expert examination to determine the market value of the completed work. If it is established that the price was indeed inflated, the court has the right to reduce the claimed amount to a reasonable level.

Can a Contractor Recover Not Only the Cost of the Work but Also Interest for Late Payment?

Yes. If the contract provides for penalties or interest for late payment, the contractor may claim them. If the contract does not specify such terms, interest under Article 395 of the Civil Code of the Russian Federation applies—for the unlawful use of another’s funds. The interest rate is calculated based on the key rate of the Central Bank of Russia on the date of performance of the obligation.

What If the Additional Work Was Not Paid For, but the Project Has Already Been Commissioned?

Commissioning of the project may indicate that the client effectively accepted the result of the work. If the contractor can prove that the work was necessary and authorized by the client, this fact may be used in court as evidence of the contract’s performance and the client’s consent to payment.

Can Payment for Additional Work Be Recovered After Several Years?

Yes, within the statutory limitation period. According to Article 196 of the Civil Code of the Russian Federation, the general limitation period is three years from the moment the contractor became aware, or should have become aware, of the violation of their right. If the client signed the acceptance certificate but failed to make payment, the period begins from the date payment was due.

Can Payment Be Recovered If the Work Is Documented Only in Forms KS-2 and KS-3?

Forms KS-2 (Certificate of Completed Work) and KS-3 (Statement of Work Cost and Expenses) confirm the fact and value of completed work but do not replace an agreement on additional work. If the work was not included in the original contract, the court will evaluate whether these forms were signed by both parties, whether they specify the additional work, and whether the client acknowledges them. If the forms KS-2/KS-3 were prepared unilaterally by the contractor, they are not sufficient proof of the client’s consent.

Is It Necessary to Send a Claim Before Filing a Lawsuit to Recover Payment Under a Contract for Work and Services?

Yes, in the vast majority of cases. According to Part 5 of Article 4 of the Arbitration Procedure Code of the Russian Federation, the pre-trial claim procedure is mandatory if the claim concerns monetary obligations. Failure to comply with this procedure may result in the return of the lawsuit or the court leaving it without consideration. The claim must include calculations, references to documents, and a reasonable response period (usually 30 calendar days).

What If the Client Avoids Signing a Supplementary Agreement but Allowed the Work to Be Performed?

If the client was notified of the intended additional work, did not object, allowed the work to proceed, and accepted the result, the court may interpret this as implied consent. In such a case, the cost of the work may be recovered if the contractor provides supporting evidence such as notices, correspondence, acceptance certificates, and witness statements.

Can Payment for Additional Work Be Recovered If It Was Agreed Upon by Email?

Yes, if the contract allows for electronic communication, and the correspondence contains specific agreements on the scope, cost, and timing of the additional work. The full correspondence must be preserved and submitted to the court. Electronic form is acceptable if the contract provides for it or if the parties have used it in practice.

How Can It Be Proven That the Work Was Truly “Additional” and Not Part of the Main Scope?

A technical examination of the project and documentation is required. If the work was not included in the contract, estimate, or project documentation and was performed due to objective circumstances (for example, to correct hidden defects), it may be classified as additional. In disputed cases, this is determined by the court based on expert findings and case materials.

Is a Signed Acceptance Certificate Sufficient to Recover Payment for Additional Work Under a Contract for Work and Services?

No. The acceptance certificate alone does not confirm the client’s consent to pay for the additional work. It records the fact of completion but does not replace a prior agreement on the cost. If the work was not agreed upon in advance and no supplementary agreement exists, the court may refuse to grant recovery.
All questions and answers

Related articles

All articles
Contract Law Contract for work and services Russia
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

A guarantee retention is a portion of the payment under a contract for work and services that the client withholds from settlements with the contractor for the duration of the warranty period for the quality of the completed work. As a rule, a few percent of the contract price is withheld, and the amount and conditions for its return are specified in the contract. In practice, the contractor receives this money with a delay — after the agreed warranty period has expired or after other conditions have been met (for example, the commissioning of the facility), provided that the client has no claims regarding the quality of the work.

Contract Law Contract for work and services Russia
How to Recover Payment for Additional Work Under a Contract For Work and Services?

How to Recover Payment for Additional Work Under a Contract For Work and Services?

A contract for work and services assumes that the contractor performs the agreed scope of work for a specified price. However, in practice, additional work often arises that was not included in the original estimate or technical documentation. The issue of payment for such work frequently becomes a stumbling block between the client and the contractor. This article explains when the client is obliged to pay for additional work, how to document it properly, and what actions the contractor should take if payment cannot be obtained.

Contract Law Contract for work and services Russia
How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

Disputes in construction regarding the quality of design documentation and the scope of work are common. Often, when facing the customer’s claims, the contractor tries to justify themselves by referring to alleged “defects” in the project documentation or unforeseen circumstances, as well as by arguing that the initial work volume was underestimated. In other words, the contractor asserts that additional work had to be performed beyond the scope of the contract or that the quality of the result suffered due to circumstances beyond their control.

In such cases, the customer has the right to challenge the contractor’s arguments. Such conflicts are governed by Chapter 37 of the Civil Code of the Russian Federation on contracts for work and services and are generally considered by arbitration courts.

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных