EN

RU CN

Date:

21.11.2025

Reading time:

6 minutes

Author:

Daniil Kadyrov

Managing Partner

How to Recover Payment for Additional Work Under a Contract For Work and Services?

Contract Law Contract for work and services

Date:

21.11.2025

Reading time:

6 minutes

FAQ

What If the Client Claims the Cost of Additional Work Was Overstated?

In this case, the court may appoint a construction and technical expert examination to determine the market value of the completed work. If it is established that the price was indeed inflated, the court has the right to reduce the claimed amount to a reasonable level.

Can a Contractor Recover Not Only the Cost of the Work but Also Interest for Late Payment?

Yes. If the contract provides for penalties or interest for late payment, the contractor may claim them. If the contract does not specify such terms, interest under Article 395 of the Civil Code of the Russian Federation applies—for the unlawful use of another’s funds. The interest rate is calculated based on the key rate of the Central Bank of Russia on the date of performance of the obligation.

What If the Additional Work Was Not Paid For, but the Project Has Already Been Commissioned?

Commissioning of the project may indicate that the client effectively accepted the result of the work. If the contractor can prove that the work was necessary and authorized by the client, this fact may be used in court as evidence of the contract’s performance and the client’s consent to payment.

Can Payment for Additional Work Be Recovered After Several Years?

Yes, within the statutory limitation period. According to Article 196 of the Civil Code of the Russian Federation, the general limitation period is three years from the moment the contractor became aware, or should have become aware, of the violation of their right. If the client signed the acceptance certificate but failed to make payment, the period begins from the date payment was due.

Can Payment Be Recovered If the Work Is Documented Only in Forms KS-2 and KS-3?

Forms KS-2 (Certificate of Completed Work) and KS-3 (Statement of Work Cost and Expenses) confirm the fact and value of completed work but do not replace an agreement on additional work. If the work was not included in the original contract, the court will evaluate whether these forms were signed by both parties, whether they specify the additional work, and whether the client acknowledges them. If the forms KS-2/KS-3 were prepared unilaterally by the contractor, they are not sufficient proof of the client’s consent.

Is It Necessary to Send a Claim Before Filing a Lawsuit to Recover Payment Under a Contract for Work and Services?

Yes, in the vast majority of cases. According to Part 5 of Article 4 of the Arbitration Procedure Code of the Russian Federation, the pre-trial claim procedure is mandatory if the claim concerns monetary obligations. Failure to comply with this procedure may result in the return of the lawsuit or the court leaving it without consideration. The claim must include calculations, references to documents, and a reasonable response period (usually 30 calendar days).

What If the Client Avoids Signing a Supplementary Agreement but Allowed the Work to Be Performed?

If the client was notified of the intended additional work, did not object, allowed the work to proceed, and accepted the result, the court may interpret this as implied consent. In such a case, the cost of the work may be recovered if the contractor provides supporting evidence such as notices, correspondence, acceptance certificates, and witness statements.

Can Payment for Additional Work Be Recovered If It Was Agreed Upon by Email?

Yes, if the contract allows for electronic communication, and the correspondence contains specific agreements on the scope, cost, and timing of the additional work. The full correspondence must be preserved and submitted to the court. Electronic form is acceptable if the contract provides for it or if the parties have used it in practice.

How Can It Be Proven That the Work Was Truly “Additional” and Not Part of the Main Scope?

A technical examination of the project and documentation is required. If the work was not included in the contract, estimate, or project documentation and was performed due to objective circumstances (for example, to correct hidden defects), it may be classified as additional. In disputed cases, this is determined by the court based on expert findings and case materials.

Is a Signed Acceptance Certificate Sufficient to Recover Payment for Additional Work Under a Contract for Work and Services?

No. The acceptance certificate alone does not confirm the client’s consent to pay for the additional work. It records the fact of completion but does not replace a prior agreement on the cost. If the work was not agreed upon in advance and no supplementary agreement exists, the court may refuse to grant recovery.
All questions and answers

Related articles

All articles
Civil Law Contract Law Dispute Resolution Leasing Claims Russia
Mandatory Pre-Trial Claim Procedure in Equipment Leasing Disputes

Mandatory Pre-Trial Claim Procedure in Equipment Leasing Disputes

Navigating commercial leasing disputes requires strict adherence to mandatory pre-trial dispute resolution protocols, which serve as an essential procedural prerequisite before initiating litigation in arbitration courts. Under current legal frameworks, ignoring this stage triggers severe procedural consequences, including the return of the statement of claim or its dismissal without prejudice. For international lessors, corporate executives, and legal counsel managing cross-border commercial assets, mastering pre-trial compliance, calculation transparency, and settlement mechanisms is vital to securing financial recovery and protecting contractual rights.

Civil Law Contract Law Procedural Law Letter of Guarantee Debt Collection Dispute Resolution Russia
Debt Payment Guarantee Letters in B2B and Commercial Practice

Debt Payment Guarantee Letters in B2B and Commercial Practice

By 2026, debt payment guarantee letters remain one of the most effective commercial instruments for balancing business relationship preservation with the formal immobilization of repayment obligations in Russia. For international investors, corporate executives, and legal professionals, a guarantee letter bridges the operational gap between overdue commercial receivables and disciplined settlement. Rather than serving as an abstract promise or an independent contractual novation, a properly structured guarantee letter establishes an unassailable legal acknowledgment of debt, locking in payment timelines and securing critical evidentiary advantages for subsequent dispute resolution.

Civil Law Contract Law Procedural Law Claims Debt Collection Debt Recovery Dispute Resolution
Preparing and Serving a Pre-Trial Debt Recovery Claim

Preparing and Serving a Pre-Trial Debt Recovery Claim

By 2026, overdue debt volumes across consumer and commercial sectors in Russia remain a primary operational hurdle for enterprises and financial institutions, driving the need for disciplined pre-trial enforcement. Under current legal frameworks, a pre-trial debt recovery claim is rarely a mere administrative formality; for many commercial and statutory disputes, it represents a mandatory procedural prerequisite before initiating litigation, as well as an essential mechanism for resolving financial disputes without entering formal enforcement proceedings or bankruptcy. Mastering the strategic formulation, calculation, and delivery of a pre-trial claim ensures robust positioning in both settlement negotiations and court proceedings.

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных