EN

RU CN

Date:

18.11.2025

Reading time:

24 minutes

Author:

Daniil Kadyrov

Managing Partner

How to Recover an Advance Payment under a Contract for Work and Labour if the Work Has Not Been Performed

Contract Law Contract for work and services

Date:

18.11.2025

Reading time:

24 minutes

FAQ

Can an advance payment be recovered if the client unilaterally terminates the contract?

Yes. If the client’s withdrawal from the contract for work and labour complies with Article 717 of the Civil Code of the Russian Federation, the contractor must return the portion of the advance payment that exceeds the value of the work actually completed. The withdrawal must be made in writing and sent to the contractor with confirmation of receipt.

Should interest be charged on the amount of the advance payment when it is being recovered?

Yes. When recovering an advance payment under a contract for work and labour, the client is entitled to claim interest for the use of another’s funds under Article 395 of the Civil Code of the Russian Federation. Interest is calculated for the entire period from the date the contractor was obliged to return the advance payment until the date of actual repayment.

What is the time limit for filing a court claim to recover an advance payment under a contract for work and labour?

The general limitation period is three years from the date when the client became aware, or should have become aware, of the violation of their right—for example, of the contractor’s failure to perform the work.

Can an advance payment under a construction contract be recovered if the contractor has violated the deadlines?

Yes. Article 715 of the Civil Code of the Russian Federation allows the client to withdraw from a construction contract in the event of a significant delay in performance. In this case, the contractor must return the advance payment in the part not covered by the cost of the work actually completed and accepted by the client.

What should be done if the contractor refuses to return the advance payment?

In such a situation, the client should take the following steps: send a written claim demanding the return of the advance payment, document the non-performance of work under the contract, and, in case of refusal, file a claim with the commercial court to recover the advance payment and interest under Article 395 of the Civil Code of the Russian Federation. After obtaining a court decision, enforcement proceedings or recovery through the contractor’s bank should be initiated.

Can an advance payment under a contract for work and labour be recovered if the work was partially completed?

Yes. The client is entitled to recover that portion of the advance payment which has not been earned by the contractor. To do this, the value of the work actually performed and accepted by the client is determined, and the difference is recovered as unjust enrichment.

How can the fact of non-performance of work by the contractor be documented for the purpose of recovering an advance payment?

The fact of non-performance under a contract for work and labour can be documented by inspection reports, technical supervision reports, expert opinions, as well as photographic and video evidence. Additionally, the client may send the contractor a formal request to provide acceptance certificates (forms KS-2, KS-3) or other documents confirming the completion of work.

Is it necessary to follow a pre-trial procedure when recovering an advance payment under a contract for work and labour?

Yes. In disputes between business entities, it is necessary to send the contractor a written claim demanding the return of the advance payment under the contract for work and labour. The claim must include a calculation of the amount, the legal grounds for the return, and a deadline for voluntary compliance. This requirement is established by Article 4 of the Commercial Procedure Code of the Russian Federation and may also be expressly stipulated by the terms of the contract.
All questions and answers

Related articles

All articles
Contract Law Contract for work and services Russia
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

A guarantee retention is a portion of the payment under a contract for work and services that the client withholds from settlements with the contractor for the duration of the warranty period for the quality of the completed work. As a rule, a few percent of the contract price is withheld, and the amount and conditions for its return are specified in the contract. In practice, the contractor receives this money with a delay — after the agreed warranty period has expired or after other conditions have been met (for example, the commissioning of the facility), provided that the client has no claims regarding the quality of the work.

Contract Law Contract for work and services Russia
How to Recover Payment for Additional Work Under a Contract For Work and Services?

How to Recover Payment for Additional Work Under a Contract For Work and Services?

A contract for work and services assumes that the contractor performs the agreed scope of work for a specified price. However, in practice, additional work often arises that was not included in the original estimate or technical documentation. The issue of payment for such work frequently becomes a stumbling block between the client and the contractor. This article explains when the client is obliged to pay for additional work, how to document it properly, and what actions the contractor should take if payment cannot be obtained.

Contract Law Contract for work and services Russia
How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

Disputes in construction regarding the quality of design documentation and the scope of work are common. Often, when facing the customer’s claims, the contractor tries to justify themselves by referring to alleged “defects” in the project documentation or unforeseen circumstances, as well as by arguing that the initial work volume was underestimated. In other words, the contractor asserts that additional work had to be performed beyond the scope of the contract or that the quality of the result suffered due to circumstances beyond their control.

In such cases, the customer has the right to challenge the contractor’s arguments. Such conflicts are governed by Chapter 37 of the Civil Code of the Russian Federation on contracts for work and services and are generally considered by arbitration courts.

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных