EN

RU CN

Date:

14.11.2025

Reading time:

16 minutes

Author:

Daniil Kadyrov

Managing Partner

How to Prove the Completion of Work if the Customer Refuses to Accept It

Contract Law Contract for work and services

Date:

14.11.2025

Reading time:

16 minutes

FAQ

Can a simplified acceptance procedure be provided for in the contract?

Yes. The contract may stipulate that if no objections are submitted within a specified period, the certificate is deemed accepted (signed).

How long does court consideration of a dispute over refusal to accept contract works usually take?

On average, from two to six months in arbitration courts of first instance, although the term depends on the complexity of the case and the need to conduct expert examinations.

Is it mandatory to conduct an expert examination to prove the completion of contract works?

Not always. However, when there is a dispute about the quality or scope of the works, an expert examination often becomes decisive, especially if there are no other direct confirmations.

Can the rules on unilateral certificates be applied to contracts other than construction contracts?

Yes, by analogy under Article 6 of the Civil Code of the Russian Federation, if the procedure for submission and acceptance of work is not regulated by special rules.

What if the Customer submits written objections to the Work Completion Certificate?

Objections must be reviewed and recorded. If the disagreements are not resolved, the contractor has the right to turn to the court, attaching evidence of actual performance of the works and of the insufficiency of the Customer’s claims.

How should a unilateral Work Completion Certificate be drawn up?

The certificate must state the scope and cost of the works, the date of completion, and the signature of the contractor’s authorized representative. It is necessary to document the fact of sending the certificate to the Customer so that the date of dispatch and receipt can be proven.

What evidence of performance of contract works does the court take into account?

The most weighty evidence includes interim acceptance certificates signed by the parties, correspondence, the construction log (where applicable), expert conclusions, site inspection reports, and photo and video materials tied to date and location.

Can payment be recovered if the Work Completion Certificate is signed only by the contractor?

Yes. A court will consider such a certificate, but it will evaluate it together with other evidence: correspondence, interim certificates, photo and video materials, and expert reports.

What to do if the Customer refuses to sign the Work Completion Certificate without giving reasons?

You must send a written notice of work completion and resend the certificate with confirmation of dispatch. If there is no response, prepare a unilateral certificate and collect evidence of performance of the obligations.
All questions and answers

Related articles

All articles
Contract Law Contract for work and services Russia
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

A guarantee retention is a portion of the payment under a contract for work and services that the client withholds from settlements with the contractor for the duration of the warranty period for the quality of the completed work. As a rule, a few percent of the contract price is withheld, and the amount and conditions for its return are specified in the contract. In practice, the contractor receives this money with a delay — after the agreed warranty period has expired or after other conditions have been met (for example, the commissioning of the facility), provided that the client has no claims regarding the quality of the work.

Contract Law Contract for work and services Russia
How to Recover Payment for Additional Work Under a Contract For Work and Services?

How to Recover Payment for Additional Work Under a Contract For Work and Services?

A contract for work and services assumes that the contractor performs the agreed scope of work for a specified price. However, in practice, additional work often arises that was not included in the original estimate or technical documentation. The issue of payment for such work frequently becomes a stumbling block between the client and the contractor. This article explains when the client is obliged to pay for additional work, how to document it properly, and what actions the contractor should take if payment cannot be obtained.

Contract Law Contract for work and services Russia
How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

Disputes in construction regarding the quality of design documentation and the scope of work are common. Often, when facing the customer’s claims, the contractor tries to justify themselves by referring to alleged “defects” in the project documentation or unforeseen circumstances, as well as by arguing that the initial work volume was underestimated. In other words, the contractor asserts that additional work had to be performed beyond the scope of the contract or that the quality of the result suffered due to circumstances beyond their control.

In such cases, the customer has the right to challenge the contractor’s arguments. Such conflicts are governed by Chapter 37 of the Civil Code of the Russian Federation on contracts for work and services and are generally considered by arbitration courts.

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных