EN

RU CN

Date:

15.11.2025

Reading time:

20 minutes

Author:

Daniil Kadyrov

Managing Partner

How to Claim a Penalty for Delayed Performance of Work by a Contractor

Contract Law Contract for work and services

Date:

15.11.2025

Reading time:

20 minutes

FAQ

What is the statute of limitations for claiming a penalty under a contract for work?

The general statute of limitations is three years (Article 196 of the Civil Code). The time period starts from the day the customer knew or should have known about the delay in completing the work. For continuing violations (daily penalties), the statute of limitations is calculated separately for each day of delay.

Can a penalty be claimed under a contract for work if the work is completed, but the customer refuses to accept it?

Yes, the penalty can be claimed if the contractor can document that the work was actually completed after the deadline, and the refusal to accept it is not related to the quality or volume of the work. In such cases, having a one-sided acceptance certificate issued after proper notification of the customer serves as important evidence.

How is the penalty calculated under a contract for work in case of partial performance?

If the contract does not specify otherwise, the penalty or fine is calculated based on the value of the uncompleted portion of the work. The period of delay is determined by the deadlines set for the completion of the entire work or for a specific stage.

Can damages be claimed along with the penalty under a contract for work?

Yes, according to Article 394 of the Civil Code, the customer has the right to claim damages in addition to the penalty unless otherwise stipulated in the contract. This may be the case, for example, if another organization is hired to complete the work or if there are expenses due to downtime.

Is it necessary to send a claim before filing a lawsuit to recover the penalty under a contract for work?

Yes, if this is stipulated in the contract or required by law. For arbitration disputes between organizations or individual entrepreneurs, the pre-trial claim procedure is mandatory (Article 4, Part 5 of the Arbitration Procedural Code of the Russian Federation). Failure to comply with this procedure will result in the rejection of the claim.

Can the court reduce the penalty for delay under a contract for work?

Yes, the court can reduce the penalty if it finds that the penalty is disproportionate to the consequences of the breach of the contractual obligation. According to Article 333 of the Civil Code, the contractor must submit a motion with appropriate justification for the reduction.

Can a penalty be claimed under a contract for work if the delay was caused by the actions of the customer?

Under Article 401 of the Civil Code, the contractor is exempt from responsibility if they prove that the delay was caused by the actions or inaction of the customer, such as the untimely provision of initial data or obstacles to access to the site.

From when is the penalty for a delay in completing work under a contract calculated?

The penalty starts accruing the day after the deadline for completion of work specified in the contract. If the deadline is changed by mutual agreement, the penalty is calculated from the new date. For domestic contracts with an individual customer, the penalty begins to accrue from the moment the delay is documented.

How to claim a penalty under a contract for work when the penalty clause is absent?

If the contract for work does not specify a penalty clause, penalties can still be claimed in cases established by law. For domestic contracts involving a private individual as the customer, Article 28 of the Consumer Protection Law applies, stipulating that the contractor must pay 3% of the price of the work for each day of delay. In other cases, it is possible to claim interest under Article 395 of the Civil Code of the Russian Federation.
All questions and answers

Related articles

All articles
Contract Law Contract for work and services Russia
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

A guarantee retention is a portion of the payment under a contract for work and services that the client withholds from settlements with the contractor for the duration of the warranty period for the quality of the completed work. As a rule, a few percent of the contract price is withheld, and the amount and conditions for its return are specified in the contract. In practice, the contractor receives this money with a delay — after the agreed warranty period has expired or after other conditions have been met (for example, the commissioning of the facility), provided that the client has no claims regarding the quality of the work.

Contract Law Contract for work and services Russia
How to Recover Payment for Additional Work Under a Contract For Work and Services?

How to Recover Payment for Additional Work Under a Contract For Work and Services?

A contract for work and services assumes that the contractor performs the agreed scope of work for a specified price. However, in practice, additional work often arises that was not included in the original estimate or technical documentation. The issue of payment for such work frequently becomes a stumbling block between the client and the contractor. This article explains when the client is obliged to pay for additional work, how to document it properly, and what actions the contractor should take if payment cannot be obtained.

Contract Law Contract for work and services Russia
How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

Disputes in construction regarding the quality of design documentation and the scope of work are common. Often, when facing the customer’s claims, the contractor tries to justify themselves by referring to alleged “defects” in the project documentation or unforeseen circumstances, as well as by arguing that the initial work volume was underestimated. In other words, the contractor asserts that additional work had to be performed beyond the scope of the contract or that the quality of the result suffered due to circumstances beyond their control.

In such cases, the customer has the right to challenge the contractor’s arguments. Such conflicts are governed by Chapter 37 of the Civil Code of the Russian Federation on contracts for work and services and are generally considered by arbitration courts.

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных