EN

RU CN

Date:

15.11.2025

Reading time:

20 minutes

Author:

Daniil Kadyrov

Managing Partner

How to Claim a Penalty for Delayed Performance of Work by a Contractor

Contract Law Contract for work and services

Date:

15.11.2025

Reading time:

20 minutes

FAQ

What is the statute of limitations for claiming a penalty under a contract for work?

The general statute of limitations is three years (Article 196 of the Civil Code). The time period starts from the day the customer knew or should have known about the delay in completing the work. For continuing violations (daily penalties), the statute of limitations is calculated separately for each day of delay.

Can a penalty be claimed under a contract for work if the work is completed, but the customer refuses to accept it?

Yes, the penalty can be claimed if the contractor can document that the work was actually completed after the deadline, and the refusal to accept it is not related to the quality or volume of the work. In such cases, having a one-sided acceptance certificate issued after proper notification of the customer serves as important evidence.

How is the penalty calculated under a contract for work in case of partial performance?

If the contract does not specify otherwise, the penalty or fine is calculated based on the value of the uncompleted portion of the work. The period of delay is determined by the deadlines set for the completion of the entire work or for a specific stage.

Can damages be claimed along with the penalty under a contract for work?

Yes, according to Article 394 of the Civil Code, the customer has the right to claim damages in addition to the penalty unless otherwise stipulated in the contract. This may be the case, for example, if another organization is hired to complete the work or if there are expenses due to downtime.

Is it necessary to send a claim before filing a lawsuit to recover the penalty under a contract for work?

Yes, if this is stipulated in the contract or required by law. For arbitration disputes between organizations or individual entrepreneurs, the pre-trial claim procedure is mandatory (Article 4, Part 5 of the Arbitration Procedural Code of the Russian Federation). Failure to comply with this procedure will result in the rejection of the claim.

Can the court reduce the penalty for delay under a contract for work?

Yes, the court can reduce the penalty if it finds that the penalty is disproportionate to the consequences of the breach of the contractual obligation. According to Article 333 of the Civil Code, the contractor must submit a motion with appropriate justification for the reduction.

Can a penalty be claimed under a contract for work if the delay was caused by the actions of the customer?

Under Article 401 of the Civil Code, the contractor is exempt from responsibility if they prove that the delay was caused by the actions or inaction of the customer, such as the untimely provision of initial data or obstacles to access to the site.

From when is the penalty for a delay in completing work under a contract calculated?

The penalty starts accruing the day after the deadline for completion of work specified in the contract. If the deadline is changed by mutual agreement, the penalty is calculated from the new date. For domestic contracts with an individual customer, the penalty begins to accrue from the moment the delay is documented.

How to claim a penalty under a contract for work when the penalty clause is absent?

If the contract for work does not specify a penalty clause, penalties can still be claimed in cases established by law. For domestic contracts involving a private individual as the customer, Article 28 of the Consumer Protection Law applies, stipulating that the contractor must pay 3% of the price of the work for each day of delay. In other cases, it is possible to claim interest under Article 395 of the Civil Code of the Russian Federation.
All questions and answers

Key Terms

C

Construction Contract

A type of contract under which the contractor undertakes to perform construction works, and the customer is obligated to accept the result and pay for it. Regulated by § 3 of Chapter 37 of the Civil Code of the Russian Federation.

C

Contractual Penalty under a Construction Contract

A sum or percentage of the debt amount established by the construction contract, payable by the customer for breaching the payment deadline.

C

Counterfault of the Customer in a Construction Contract

Circumstances in which the delay in completing work is caused by the actions or inactions of the customer, which can release the contractor from paying a penalty.

F

Fine under a Construction Contract

A type of penalty represented by a fixed monetary sum, payable upon violation of the obligation, regardless of the duration of the delay.

I

Interest under Article 395 of the Civil Code of the Russian Federation

Monetary compensation levied for delay in performing a monetary obligation. It is calculated based on the Central Bank's key rate and is applied regardless of the debtor's fault unless otherwise provided by law or contract.

L

Late Payment Penalty under a Construction Contract

A type of penalty representing a monetary sum accrued for each day or other period of delay in the performance of the obligation.

P

Penalty

A monetary sum established by law or contract that the debtor must pay the creditor in case of non-performance of the obligation. It can take the form of a fine (a fixed sum) or a penalty (accrued for each day of delay).

P

Pre-trial Procedure

A mandatory procedure for resolving disputes before going to court, involving sending a written demand to the other party for voluntary rectification of the violation. Required for most civil law and arbitration disputes unless otherwise provided by law or contract.

S

Statute of Limitations

The period during which a person has the right to apply to the court for protection of a violated right. By default, it is three years from the date the person knew or should have known about the violation of their right.

S

Statutory Penalty

A penalty whose amount and procedure for application are defined by law and apply regardless of the terms of the contract.

Related articles

All articles
Law of Obligations Contract Law Procedural Law Contract for work and services Court Representation Legal support Russia
When and How to Terminate a Contract for Services and Recover Damages

When and How to Terminate a Contract for Services and Recover Damages

The client has the right to terminate the contract by mutual agreement, unilaterally, in case of a breach by the contractor, or through the court. It is important to properly draft notifications, calculate mutual settlements, and, if necessary, recover damages. This article discusses the legal grounds, the procedure for termination, and practical recommendations to protect the client's interests.

Law of Obligations Contract Law Procedural Law Contract for work and services Legal support Russia
How to Recover Payment When the Work Has Been Accepted but Not Paid For

How to Recover Payment When the Work Has Been Accepted but Not Paid For

Once the acceptance certificate for the completed work is signed, the customer incurs an unconditional obligation to make payment in the amount and within the time limits established by the contract. This moment confirms that the contractor has fully performed its obligations regarding the work result.

Migration Law Law of Obligations Contract Law Real estate transactions and registration Legal support Mandatory payments Turkey Whole world
How to Get Your Money Back After a Residence Permit Refusal?

How to Get Your Money Back After a Residence Permit Refusal?

Refusals for issuing or renewing residence permits in Turkey have become increasingly common. Similar issues arise in other jurisdictions as well. In such cases, applicants often wonder: is it possible to get a refund for funds already paid, and how can this be done?

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных