EN

RU CN

Date:

21.11.2025

Reading time:

8 minutes

Author:

Daniil Kadyrov

Managing Partner

How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

Contract Law Contract for work and services

Date:

21.11.2025

Reading time:

8 minutes

FAQ

When does the limitation period for a claim to return the retention payment begin?

The limitation period (three years) starts from the day the client was obliged to return the retention payment according to the contract terms, or from the end of the warranty period if the date is not directly specified.

What documents must be submitted to court to recover a retention payment?

The contractor should provide: the contract for work and services, acceptance certificates (including unilateral ones if applicable), correspondence with the client, the pre-trial claim with proof of submission, documents confirming the retention amount (invoices, calculation statements), and other materials evidencing fulfillment of obligations.

Is it necessary to send a pre-trial claim to recover a retention payment?

Yes. For disputes between legal entities and individual entrepreneurs, compliance with the pre-trial claim procedure is mandatory (Part 5, Article 4 of the Arbitration Procedure Code of the Russian Federation). Failure to submit a pre-trial claim may result in the dismissal of the lawsuit.

Can interest be claimed for delayed return of the retention payment?

Yes. Under Article 395 of the Civil Code of the Russian Federation, if the retention amount is not returned on time, the contractor may claim interest for the use of another’s funds. This interest can be recovered regardless of whether a contractual penalty is provided.

Can the client withhold the retention payment due to identified defects?

Yes, but only to the extent proportionate to the cost of remedying verifiable defects if the contractor fails to correct them. Without documented justification, the client is not entitled to withhold the amount arbitrarily.

Is the retention amount considered part of the payment under the contract for work and services?

No. Judicial practice treats the retention payment as a security measure to guarantee the quality of the work performed. It is not part of the final payment but a separate obligation of the client to return the amount if there are no claims.

Can a retention payment be recovered if the contract does not include provisions for its return?

Yes. Even if the contract does not contain specific terms regarding the return of retention payments, the contractor is entitled to recover the amount upon expiration of the warranty period, provided that obligations were fulfilled and no defects were found. This follows from the principles of good faith and consideration under the contract (Articles 421 and 702 of the Civil Code of the Russian Federation).

What should a contractor do if the client refuses to sign the acceptance certificate under the contract for work and services?

The contractor may prepare a unilateral acceptance certificate if the work has been effectively delivered and the client refuses to sign without valid reasons. Such a certificate, together with supporting documents, can be recognized by the court as sufficient evidence of work completion.

Is the client obliged to return the retention payment if there are no quality claims?

Yes. In the absence of justified claims regarding the quality of the completed work, the client is required to return the retention payment within the period specified in the contract. Failure to do so constitutes a breach of Articles 309 and 310 of the Civil Code of the Russian Federation and gives the contractor the right to recover the debt and interest for the use of their funds.
All questions and answers

Related articles

All articles
Contract Law Contract for work and services Russia
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services

A guarantee retention is a portion of the payment under a contract for work and services that the client withholds from settlements with the contractor for the duration of the warranty period for the quality of the completed work. As a rule, a few percent of the contract price is withheld, and the amount and conditions for its return are specified in the contract. In practice, the contractor receives this money with a delay — after the agreed warranty period has expired or after other conditions have been met (for example, the commissioning of the facility), provided that the client has no claims regarding the quality of the work.

Contract Law Contract for work and services Russia
How to Recover Payment for Additional Work Under a Contract For Work and Services?

How to Recover Payment for Additional Work Under a Contract For Work and Services?

A contract for work and services assumes that the contractor performs the agreed scope of work for a specified price. However, in practice, additional work often arises that was not included in the original estimate or technical documentation. The issue of payment for such work frequently becomes a stumbling block between the client and the contractor. This article explains when the client is obliged to pay for additional work, how to document it properly, and what actions the contractor should take if payment cannot be obtained.

Contract Law Contract for work and services Russia
How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume

Disputes in construction regarding the quality of design documentation and the scope of work are common. Often, when facing the customer’s claims, the contractor tries to justify themselves by referring to alleged “defects” in the project documentation or unforeseen circumstances, as well as by arguing that the initial work volume was underestimated. In other words, the contractor asserts that additional work had to be performed beyond the scope of the contract or that the quality of the result suffered due to circumstances beyond their control.

In such cases, the customer has the right to challenge the contractor’s arguments. Such conflicts are governed by Chapter 37 of the Civil Code of the Russian Federation on contracts for work and services and are generally considered by arbitration courts.

All articles

Contact us

Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.

Имя *
Это поле обязательно для заполнения
Телефон *
Это поле обязательно для заполнения
E-mail
Введён некорректный e-mail
Сообщение
Необходимо ваше согласие на обработку персональных данных