Date:
21.11.2025
Reading time:
8 minutes
Author:
Daniil Kadyrov
Managing Partner
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services
Date:
21.11.2025
Reading time:
8 minutes
FAQ
When does the limitation period for a claim to return the retention payment begin?
What documents must be submitted to court to recover a retention payment?
Is it necessary to send a pre-trial claim to recover a retention payment?
Can interest be claimed for delayed return of the retention payment?
Can the client withhold the retention payment due to identified defects?
Is the retention amount considered part of the payment under the contract for work and services?
Can a retention payment be recovered if the contract does not include provisions for its return?
What should a contractor do if the client refuses to sign the acceptance certificate under the contract for work and services?
Is the client obliged to return the retention payment if there are no quality claims?
Related articles
All articles
How a Contractor Can Recover a Retention Payment Under a Contract for Work and Services
A guarantee retention is a portion of the payment under a contract for work and services that the client withholds from settlements with the contractor for the duration of the warranty period for the quality of the completed work. As a rule, a few percent of the contract price is withheld, and the amount and conditions for its return are specified in the contract. In practice, the contractor receives this money with a delay — after the agreed warranty period has expired or after other conditions have been met (for example, the commissioning of the facility), provided that the client has no claims regarding the quality of the work.
How to Recover Payment for Additional Work Under a Contract For Work and Services?
A contract for work and services assumes that the contractor performs the agreed scope of work for a specified price. However, in practice, additional work often arises that was not included in the original estimate or technical documentation. The issue of payment for such work frequently becomes a stumbling block between the client and the contractor. This article explains when the client is obliged to pay for additional work, how to document it properly, and what actions the contractor should take if payment cannot be obtained.
How to Challenge a Contractor’s Reference to Design Defects and Underestimation of Work Volume
Disputes in construction regarding the quality of design documentation and the scope of work are common. Often, when facing the customer’s claims, the contractor tries to justify themselves by referring to alleged “defects” in the project documentation or unforeseen circumstances, as well as by arguing that the initial work volume was underestimated. In other words, the contractor asserts that additional work had to be performed beyond the scope of the contract or that the quality of the result suffered due to circumstances beyond their control.
In such cases, the customer has the right to challenge the contractor’s arguments. Such conflicts are governed by Chapter 37 of the Civil Code of the Russian Federation on contracts for work and services and are generally considered by arbitration courts.
Contact us
Leave a request and our lawyers will contact you as soon as possible to provide a free consultation on your issue.